The dark gray siding is all up now. They still have some vertical board and batten siding to put up in the gables. The weather hasn't cooperated to allow that to happen. The weather has caused other delays as well, there is about two squares of roofing missing thanks to the wind. Unfortunately, this is going to keep happening until the shingles get some warm weather.
Otherwise, inside work has continued. The painters have been busy filling nail holes and caulking all of the joints in the trim. Today they started spraying primer on all of the trim and inside of the windows.