This last week was pretty slow due to the holiday. Thanks a lot Thanksgiving... uh, right! Anyway, they trenched power to the house and got it hooked up. I was able to do some work there as well, ran some speaker wire and built a backdrop for the windows above the front porch that look into the attic.
And then today they started hanging rock(drywall). At the rate their going it should be finished before the end of the week... hopefully.
Tuesday, November 27, 2012
Thursday, November 15, 2012
Columns and Front Gable Windows
This week they built the columns on the front porch and put the porch ceilings in. As well as the insulation has been going in and is about finished.
Wednesday, November 7, 2012
Roofing and Electrical Rough-In Finished
This week the roofers finally finished, therefore the electrical contractor was able to finish the rough-ins under a dry roof. We were very happy with the electrical contractor, he was willing to work with all of our requests and even had suggestions for added things here and there. They were awesome to work with.
The picture below is our well pump controller and pressure tank. It is a constant-pressure system that will provide constant pressure even when multiple fixtures are in use and the water pressure can be increased or decreased with the touch of a button. Pretty cool I think.
Friday, November 2, 2012
Exterior Doors Installed
This week the exterior doors were installed, the electricians are about done and the roofers made good progress despite weather from Hurricane Sandy. I love how we had almost record drought conditions all summer, but as soon as we started building there hasn't been a week WITHOUT rain or wind. Frustrating...
Subscribe to: